Dmrc Tunnel Projects

I heard that Delhi Tunnel Project was started. I want to know when it was started and when it was ended.In other way I need a brief detail about this projet.Can you provide me such detail of DMRC Tunnel Project?
Similar Threads
Thread
IIM Ahmedabad Tunnel
Eapplynew DMRC Pages DMRC Preview
DMRC Career DMRC Recruitment
Wind Tunnel IIT Delhi
DMRC Upcoming Projects In Delhi
Imt MBA projects
MBA hr projects
DMRC Tunnel
IIT Delhi Wind Tunnel
DMRC Running Projects
DMRC Ongoing Projects
IIT Kanpur Wind Tunnel
Wind Tunnel IIT Delhi
ISRO Wind Tunnel
MBA CP Projects
Ovs-Vsctl Gre Tunnel
Smu MBA hcs projects
IIT Bombay Wind Tunnel
IMT MBA Projects
MBA IB projects
  #2  
17th August 2018, 04:14 PM
Unregistered
Guest
 
Re: Dmrc Tunnel Projects

Hello sir, I want detail about tunnel project of Delhi metro rail corporation. Is there any one can tell me how many Tunnels are open during DMRC projects?
  #3  
17th August 2018, 04:15 PM
Super Moderator
 
Join Date: Aug 2012
Re: Dmrc Tunnel Projects

The DMRC has a Tunnel Boring Machines project. The Tunnel Boring Machines are used to excavate tunnels in virtually all types of grounds and under widely different physical conditions.

The history of TBMs started with soft ground shields of the type developed in England. These shields progressed by breaking the excavation in to small compartments excavated by hand.

The science of mechanical underground tunnel excavation has developed continual step by step. TBMs, also known as Moles, are the recent development in the tunnel driven techniques

The contract CC04 is part of the new 58 km long PINK LINE (Line 7) of the Delhi metro phase III project, runs from Mukundpur in the North of Delhi in circle up to Shiv Vihar in the North East.

In this project, the first 2 Earth Pressure Balance Machine (EPBM) launched at Azadpur station south Journal of Geomatics

Scope of work:


The scope of the work consists of:
Tunnel: 5.2 km bored tunnels with ID 5.80 meters
(using 4 TBM EPB Mode)
Cross passage: 1 Nos
Emergency exits: 2 Nos
Underground stations: 1 No (252m length)
Cut & cover tunnel: 1 No (96m), Ramp: 1 No (192m)

Get info about 19 Tunnel boring machines boring tunnels simultaneously the national capital`s surface DMRC:







List of 19 Tunnel boring machines boring tunnels simultaneously the national capital`s surface:


Phase 3 corridor Location of TBM No. of TBMs
Central Secretariat Kashmere Gate Kashmere Gate to Lal Quila 1

Jama Masjid to Delhi Gate 1

Majlish Park Shiv Vihar Azadpur to Mukundpur 2

Delhi Cantt. to Naraina 1
Bhikaji Cama Place to Sarojini Nagar 2

South Extension to Lajpat Nagar 2

Janakpuri West Botanical Garden Dasrathpuri to Dabri Mor 2
Terminal 1 IGI Airport to Shankar Vihar 2

Munirka to RK Puram 2
2
IIT Hauz Khas 1

Hauz Khas Panchsheel Park 2


Kalkaji Mandir Nehru Enclave 1


Quick Reply
Your Username: Click here to log in

Message:
Options




All times are GMT +5. The time now is 11:12 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
SEO by vBSEO 3.6.0 PL2

1 2 3 4