Hello, here I am providing you the details of the NTPC-TNEB joint venture project as under:

About the JV:
This JV was incorporated on 23.05.2003 with Tamil Nadu Electricity Board, a State run Electricity Board in the State of Tamil Nadu engaged in generation, transmission and distribution of electricity.

OBJECTIVE
To set up a 1500 MW coal based power station at vallur, Ennore in Tamil Nadu utilising the existing infrastructure facility at Ennore and supply power mainly to Tamil Nadu and the states of Kerala, Karnataka and Pondicherry.

PROMOTERS' EQUITY
NTPC: 50%
TNEB: 50%

Present stage of the project:
UNIT I:

Synchronization completed on 09.03.2012.
All works in Ash Handling and coal handling system completed and put in service.
The coal conveyor system includes the newly commissioned 4.4 Kms long pipe conveyor with a capacity of 4000 tonnes /hour -making it the world's largest pipe conveyor.
The unit declared on Commercial operation from 00.00 Hrs. on 29.11.2012.

UNIT II:
Boiler Light up completed on 16.07.2012.
Turbine Box Up completed.
Steam blowing first stage completed on 02.12.2012.
Unit Synchronised on 26.02.2013.
The unit declared on Commercial operation from 00.00 Hrs. on 25.08.2013.

UNIT III:
Boiler Hydro test completed on 30.09.2012.
Boiler Light up completed on 31.08.2013.
Generator Stator arrived at site.
TG box up completed.
Unit Synchronised on 28.02.2014.
The unit declared on Commercial operation from 00.00 Hrs. on 26.02.2015.


Quick Reply
Your Username: Click here to log in

Message:
Options

Thread Tools Search this Thread



All times are GMT +5. The time now is 04:35 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
SEO by vBSEO 3.6.0 PL2

1 2 3 4