Overview of NTPC Barh
I am searching for overview of Barh Super Thermal Power Station of NTPC. So is there anybody who will provide information about Barh Super Thermal Power Station of NTPC?
|
#2
20th January 2017, 05:56 PM
| |||
| |||
Re: Overview of NTPC Barh
The Barh Super Thermal Power Station was begun in 1999 by NTPC. The Power Station is situated in Bihar State. The 1,980MW (3x660 MW) Barh Stage-1 is being built by Russian firm Technopromexport (TPE), and 1,320MW (2x660 MW) Barh Stage-2 extension is being built by BHEL Bihar's share is 1183 MW from NTPC Barh(26% from stage 1 and 50% from stage 2). The main power plant and the township is spread over an area of 1,186 acres. The plant is to produce 3,300MW of power at a cost of over Rs 26,000 crore. Capacity Stage Unit Number Capacity (MW) EPC Contractor 1st 1 660 MW Technopromexport 2 660 MW Technopromexport 3 660 MW Technopromexport 2nd 4 660 MW Bharat Heavy Electricals 5 660 MW Bharat Heavy Electricals Total Five 3300 MW |