As you are looking to get information about Panipat Naphtha Cracker Project of IOCL, so here is following details:

Panipat Naphtha Cracker Project of IOCL
Mode of Execution
Pre FEED, FEED & PMC

Key Features
Overall Capacity:
800 KTA Ethylene
660 KTA Propylene


Major Processing Units :
HGU, Pyrolysis Gasoline Hydrogenation, Benzene Extraction Unit, PPU, LLDPE/HDPE Swing Unit, HDPE, Utility Boilers, Cooling Tower, DM Plant, Effluent Treatment Plant, O2/N2 Plant, Offsite Storage and Dispatch facility

Total Project Cost
USD 2.4 billion

Schedule
42 months -





UNIQUE CHALLENGES
Process & Engineering
Zero Effluent discharge from the complex. Designed for 100% re-use of facility.
Liquid effluent treatment conformed to the MINAS statutory Standards.

Procurement
Procurement of following items through 54 nos Indian vendors and 18 nos foreign vendors
300 nos of Equipments
50 nos of Piping
30 nos of Instrumentation
17 nos of Electricals

ACHIEVEMENT
HSE
75 million Construction Man-hour achieved without Lost Time Accident.

Cost Saving
More than Rs.300 Crores savings to client on estimated project cost after award of LSTK contract to EIL.

Schedule Saving
128 days time saving w. r. t actual completion for world scale size naphtha cracker complex.
Project completion in 46 months is the lowest time schedule at global level


Quick Reply
Your Username: Click here to log in

Message:
Options

Thread Tools Search this Thread



All times are GMT +5. The time now is 06:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
SEO by vBSEO 3.6.0 PL2

1 2 3 4