As per your request here I am sharing the last year question paper of CSTE Certification Exam

1. The customer’s view of quality means:
a. Meeting requirements
b. Doing it the right way
c. Doing it right the first time
d. Fit for use
e. Doing it on time
2. The testing of a single program, or function, usually performed by the developer is called:
a. Unit testing
b. Integration testing
c. System testing
d. Regression testing
e. Acceptance testing
3. The measure used to evaluate the correctness of a product is called the product:
a. Policy
b. Standard
c. Procedure to do work
d. Procedure to check work
e. Guideline
4. Which of the four components of the test environment is considered to be the most important component of the test environment:
a. Management support
b. Tester competency
c. Test work processes
d. Testing techniques and tools
5. Effective test managers are effective listeners. The type of listening in which the tester is performing an analysis of what the speaker is saying is called:
a. Discriminative listening
b. Comprehensive listening
c. Therapeutic listening
d. Critical listening
e. Appreciative listening
6. To become a CSTE, an individual has a responsibility to accept the standards of conduct defined by the certification board. These standards of conduct are called:
a. Code of ethics
b. Continuing professional education requirement
c. Obtaining references to support experience
d. Joining a professional testing chapter
e. Following the common body of knowledge in the practice of software testing
7. Which of the following are risks that testers face in performing their test activities:
a. Not enough training
b. Lack of test tools
c. Not enough time for testing
d. Rapid change
e. All of the above
8. All of the following are methods to minimize loss due to risk. Which one is not a method to minimize loss due to risk:
a. Reduce opportunity for error
b. Identify error prior to loss
c. Quantify loss
d. Minimize loss
e. Recover loss

9. Defect prevention involves which of the following steps:
a. Identify critical tasks
b. Estimate expected impact
c. Minimize expected impact
d. a, b and c
e. a and b
10. The first step in designing use case is to:
a. Build a system boundary diagram
b. Define acceptance criteria
c. Define use cases
d. Involve users
e. Develop use cases
11. The defect attribute that would help management determine the importance of the defect is called:
a. Defect type
b. Defect severity
c. Defect name
d. Defect location
e. Phase in which defect occurred
12. The system test report is normally written at what point in software development:
a. After unit testing
b. After integration testing
c. After system testing
d. After acceptance testing
13. The primary objective of user acceptance testing is to:
a. Identify requirements defects
b. Identify missing requirements
c. Determine if software is fit for use
d. Validate the correctness of interfaces to other software systems
e. Verify that software is maintainable
14. If IT establishes a measurement team to create measures and metrics to be used in status reporting, that team should include individuals who have:
a. A working knowledge of measures
b. Knowledge in the implementation of statistical process control tools
c. A working understanding of benchmarking techniques
d. Knowledge of the organization’s goals and objectives
e. All of the above
15. What is the difference between testing software developed by a contractor outside your country, versus testing software developed by a contractor within your country:
a. Does not meet people needs
b. Cultural differences
c. Loss of control over reallocation of resources
d. Relinquishment of control
e. Contains extra features not specified
16. What is the definition of a critical success factor:
a. A specified requirement
b. A software quality factor
c. Factors that must be present
d. A software metric
e. A high cost to implement requirement
17. The condition that represents a potential for loss to an organization is called:
a. Risk
b. Exposure
c. Threat
d. Control
e. Vulnerability
18. A flaw in a software system that may be exploited by an individual for his or her advantage is called:
a. Risk
b. Risk analysis
c. Threat
d. Vulnerability
e. Control
19. The conduct of business of the Internet is called:
a. e-commerce
b. e-business
c. Wireless applications
d. Client-server system
e. Web-based applications
20. The following is described as one of the five levels of maturing a new technology into an IT organization’s work processes. The “People-dependent technology” level is equivalent to what level in SEI’s compatibility maturity model:
a. Level 1
b. Level 2
c. Level 3
d. Level 4
e. Level 5


Quick Reply
Your Username: Click here to log in

Message:
Options




All times are GMT +5. The time now is 08:59 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
SEO by vBSEO 3.6.0 PL2

1 2 3 4