Here is the list of few questions of CPWD Civil Engineering Exam Question Paper which you are looking for .

1.
Which one of the following represents an activity
A.excavation for foundation
B.curing of concrete
C.setting of question paper
D.preparation of breakfast
E.all the above.

2.
Pick up the incorrect statement from the following:
A.An activity of a project is denoted by an arrow on the net work
B.The tail of the arrow indicates the start of the activity
C.The head of the arrow indicates the end of the activity
D.The arrows are drawn to scale from left to right
E.Each activity consumes a given time.

3.
The technique for establishing and maintaining priorities among the various jobs of a project, is known
A.Event flow scheduling technique
B.Critical ratio scheduling
C.Slotting technique for scheduling
D.Short interval scheduling.

4.
Mile Stone charts were invented in the year of
A.1910B.1920
C.1930D.1940
E.1950

5.
Frederick W. Taylor introduced a system of working known as
A.line organisation
B.line and staff organisation
C.functional organisation
D.effective organisation.

6.
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
A.
B.
C.
D.
E.

7.
In the given figure, the network of a project represents
A.activity of an excavation of a footing
B.activity of an excavation which starts at event No. 1 and ends at even No. 2
C.activity of excavation which takes 8 units of time
D.none of these.

8.
The cost of a project is more than
A.one lac
B.two lacs
C.three lacs
D.four lacs
E.five lacs.

9.
Pick up the PERT event from the following:
A.Digging of foundation started
B.Digging of foundation completed
C.Laying of concrete started
D.Laying of concrete completed
E.All the above.

10.
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
A.EF = ES + D
B.LS = LF - D
C.LF = LS + D
D.D = EF - ES
E.all the above.

11.
Final technical authority of a project lies with
A.Assistant Engineer
B.Executive Engineer
C.Superintending Engineer
D.Chief Engineer.

12.
The performance of a specific task in CPM, is known
A.DummyB.Event
C.ActivityD.Contract.

13.
Pick up the correct statement from the following:
A.The float may be positive, zero or negative
B.If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
C.If the float of an activity is negative, delay in its performance is bound to delay the completion of project
D.If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
E.All the above.

14.
A Milestone chart
A.shows the interdependencies of various jobs
B.depicts the delay of jobs, if any
C.points outgoing ahead of schedule of jobs, if any
D.none of these.

15.
Completion of an activity on CPM network diagram, is generally known
A.Event
B.Node
C.Connector
D.All the above.


Quick Reply
Your Username: Click here to log in

Message:
Options




All times are GMT +5. The time now is 12:34 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
SEO by vBSEO 3.6.0 PL2

1 2 3 4